Hello! We are pursuing the Integrative Analysis of Buildling Materials Pilot Credit # 103. The reviewer is asking for the Integrative Analysis spreadhseet to be filled out. I have the spreadsheet downloaded, but it's indecipherable. Anyone have a clue as to how this form works? It seems to have Macros that are not loading. There are no instructions to the form. Any help would be appreciated.
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Olga Yuil
Green Building Consultant20 thumbs up
May 4, 2022 - 4:39 pm
Hi Brian!
Did you read the Integrative Analysis of Building Materials - Guidance (https://www.usgbc.org/resources/integrative-analysis-guidance)?
Hope it helps.
Brian Salazar
President, LEED AP, WELL APEntegra Development & Investment, LLC
56 thumbs up
May 5, 2022 - 10:08 am
Thanks Olga - So, do I just copy the information from the manufacturer's report into this same grid and submit it? The additionalguideance states, "As mentioned previously, the pilot credit’s intent is to provide project teams a way to identify relevant lifecycle, environmental, and health data to inform product selection in a quick, easy to use manner. That notwithstanding, some project teams may want to provide additional, more detailed information on these impacts." Seems like adding to this form is optional?
Olga Yuil
Green Building Consultant20 thumbs up
May 5, 2022 - 4:27 pm
Hi Brian,
We attempted and achieved this pilot credit in version 4 (https://www.usgbc.org/credits/new-construction-core-and-shell-schools-ne...) for a NCv4 project.
Not sure if there are big differences between the v4 and v4.1 pilot credit.
In my version 4 experience POTENTIAL HUMAN HEALTH IMPACTS and POTENTIAL ENVIRONMENTAL IMPACTS are impacts that can be extracted from the material or product technical documentation (MSD, SDS, TDS, EPD, HPD, C2C, GLP Certificate, Declare label, Greenguard certificate, product maintenance guide and others and others and others).
POTENTIAL SAFETY IMPACTS come rather from a brainstorming of the project team and qualitative characteristics of the product.
Please make sure to within the worksheet avoid: empty or not applicable (NA) or no impact responses.
When the worksheet is complete, upload it and also updload all the technical documentation used for all the three product/materials required. And also upload the pilot credit feedback survey email.
Brian Salazar
President, LEED AP, WELL APEntegra Development & Investment, LLC
56 thumbs up
May 17, 2022 - 11:14 am
Thanks Olga - I will modify our response and fill in the form fromthe data that the manufacturer provides for these products.