Hi Folks,
Is prescriptive compliance Option 2 (EA - Minimum Energy Performance) an option for Core and shell projects (Expected occupancy - Office) with GFA greater than 100,000 SF? ASHRAE AEDG for office buildings applies to area less than 100,000 SF.
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5909 thumbs up
April 22, 2022 - 8:48 am
Prescriptive compliance is not an option for an office greater than 100k sf. You are required to use option 1.