I got a renovation project of the 7 stories existing building to the office which aims to be LEED-CS but the project contains zero lot line. Is it possible to pass this prerequisite?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Andrey Kuznetsov
ESG consultant, LEED AP BD+CSelf Employed
33 thumbs up
March 30, 2022 - 9:54 am
According to refguide, page 260: "Projects with no landscape area are exempt from this prerequisite"
Somsak Jidmon
Senior Architect and LEED ConsultantGA Studio Co.,LTD.
1 thumbs up
March 30, 2022 - 10:16 am
Thank you.