Has anyone used ASHRAE 90.1-2016 as a baseline for a v4 project and know what the adjustment in points would be for this baseline? I know USGBC made adjustments for a 90.1-2013 baseline, but I haven't seen anything for 2016.
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for $15.95 »
Michelle Christopher
Buro Happold5 thumbs up
April 23, 2021 - 1:38 pm
LEED v4.1 uses ASHRAE 90.1-2016 so my guess is that you would need to use the v4.1 scale. ASHRAE 90.1-2016 introduces the Performance Cost Index (PCI) calculation so the savings would not align the same way to a v4 project that uses 90.1-2010.