1. Modify the first paragraph in Option 2. Air Testing so it reads: "Conduct baseline IAQ testing, after construction ends and within 14 days following occupancy, using testing protocols consistent with the EPA Compendium of Methods for the Determination of Air Pollutants in Indoor Air or as the ISO method listed in the table below. Testing must be done in accordance with one standard; project teams may not mix requirements from the EPA Compendium of Methods with ISO."
2. Modify the first bullet in Option 2. Air Testing so it reads: "All measurements must be conducted prior to occupancy or within 14 days following occupancy, but during normal occupied hours with the building ventilation system started at the normal daily start time and operated at the minimum outside air flow rate for the occupied mode throughout the test."