Step-by-Step Guidance, Step 1 changes:
Under the sentence "Before the performance period begins, calibrate any building-owned meters to the manufacturer's recommended interval" in Step 1, make the following changes to the second bullet in the bulleted list:
- Add "-ed" to the end of "own" so that the phrase in the second bullet reads "Meters owned by tenants must be included and should be calibrated before the performance period."
- Add the following sentence to the end of the second bullet: "Multifamily projects with non-master metered utilities can collect a statistically significant sampling of utility data from the residential unit space. Projects should refer to USGBC's Residential Utility Sampling Protocols."
- Link "USGBC's Residential Utility Sampling Protocols" text to the following webpage: http://www.usgbc.org/resources/eb-oampm-residential-utility-sampling-pro...