At the end of the Establishment requirements, add:
Multifamily only
Meet the above requirements. Major end uses for multifamily projects may be defined as central building systems that represent 20% or more of the total annual energy consumption of the building.

Install an electricity meter for each unit.
At the end of the Performance requirements, add:

Multifamily only
On at least a monthly basis, provide residents access to their individual unit electricity consumption data.

On at least a monthly basis, report the facility’s utility peak demand and total consumption and compare it with the data for the previous month and the same month from the previous year.

Date
Updated date
Campus Applicable
Off
Internationally Applicable