Revise the credit requirements to include Options as follows:

"Option 1. Purchase 20% by cost of permanently installed top three infrastructure materials
Comply with one or more of the following criteria for minimum 20% of total infrastructure material cost for permanently installed top three materials used in infrastructure. (1 point)

OR

Option 2. Purchase 40% by cost of permanently installed top five infrastructure materials
Comply with one or more of the following criteria for minimum 40% of total infrastructure material cost for permanently installed top five materials used in infrastructure. (2 points)"

In the Cities: Existing Rating System only:

Revise the second paragraph under Option 2 to read as:

"Include new construction, major renovation, repair or demolition works undertaken or contracted by the local government for a full calendar year within the past five years. Infrastructure includes but is not limited to roads and highways, transits, water supply and wastewater treatment plants, public spaces and parks."

Date
Updated date
Campus Applicable
Off
Internationally Applicable
Off