Inquiry

If a project team is demolishing an existing school and rebuilding it on the same site, is a Phase I ESA still required?

Ruling

A Phase I Environmental Site Assessment (as described in ASTM E1527-05) is required of all school projects, even if the site\'s history is known, to ensure that the prerequisite intent is met. Applicable internationally.