Inquiry

Can a third party such as a utility company install and operate a Solar PV system on the rooftop of a LEED project, and can the owner achieve EA c2 credit (1%) and possibly an exemplary performance credit (5%) for Core and Shell V2.0 rating system? Intent of Credit: Encourage and recognize increasing levels of on-site renewable energy self-supply in order to reduce environmental and economic impacts associated with fossil fuel energy use. Approach: A new program has been initiated in the San Diego Gas and Electric (SDG&E)territory named Clean Energy Systems. The objective of this program is to find usable roof space (at least 5,000 sf)in high performance buildings such as this project where a Solar PV system can be installed, operated, and maintained by SDG&E. The impetus for this unique program is to use available secure roof top space to increase its renewable energy system portfolio that will help SDG&E get to its 20% overall renewable energy portfolio as required by California State Law. It would be the intent of SDG&E to sign a long-term lease space contract with the Owner of this project and install at least 5,000 sf of Solar PV array up on the roof of this and possibly the other two future buildings (Buildings B and C)in this core and shell complex. As mentioned previously, the motivation of SDG&E will be to grid-tie this renewable energy to assist them in achieving the 20% portfolio threshold. The motivation of the Owner is to achieve at least one and maybe two LEED points even though they will not necessarily be using electricity generated from the Solar PV system. The owner would sign a contract with SDG&E before this project is submitted via LEED Online sometime in the Fall of this year 2008. We would provide evidence to this plus an implementation schedule for installation of the system on at least Building A during design submittals. Confirmation of Credit Intent: We believe this approach does meet the intent of the credit providing renewable energy self-supply in order to reduce the environmental effects of fossil fuel consumption (aka global warming)while providing the developer with very needed LEED points in order to achieve LEED Silver for its Building A project. We also believe that this approach will be occurring more frequently in the near future with progressive utilities offering to lease roof space on LEED-registered buildings for independent Solar PV farms. Please verify that this approach summarized above does fulfill the intent of Credit EA c2.

Ruling

The installation of on-site renewable energy sources owned and operated by an entity other than the building owner is allowable for achievement of EAc2 and has been addressed by a previous CIR dated 7/19/2007, provided the following conditions are met: [1] The renewable energy system must be installed within the boundaries of the project or on the project site. [2] The renewable energy system is connected immediately adjacent to the utility meter. [3] A 10-year (minimum) contract for on-site generation with the owner of the energy system must be established. [4] The Renewable Energy Credits (RECs) associated with the renewable energy system may not be sold. [5] The renewable energy system owner may not count the RECs associated with the renewable energy system to meet a mandated renewable portfolio standard goal or provide RECs to the project owner. The proposed renewable energy system does not appear to meet condition [5] since SDG&E is proposing the renewable energy system installation in order to meet a 20% renewable energy portfolio goal. Applicable Internationally.

Internationally Applicable
On
Campus Applicable
Off