Inquiry

Can a project earn certification without any landscaping installed? How should the SS prerequisites and credits be handled?

Ruling

Projects that choose or are unable to install landscaping (e.g. production builders, projects finishing during winter) may be certified on the following conditions: 1) a landscaping plan must be developed and provided to the homeowner that includes no invasive plants; (2) information or references about native and drought-tolerant plants must be provided to the homeowner; and 3) no points may be awarded in SS 2, SS 3 (a), SS 4.2 (b), or SS 5 (d). Half-credit may be granted for SS 4.1, but only if all final hardscapes are installed, including driveways, walkways, patios, etc. No credit may be awarded for SS 4.3 unless infiltration features are installed.