We are planning on performing a 2 week building flush out as required by EQ cr3.2. Due to schedule constraints, it would be helpful if the Owner were allowed to set up used, moveable office partitions, and install new auditorium seating during the flush out period. The used, moveable office partitions are from another building, and have, theoretically, already off-gassed. Would it be acceptable to perform one or both of these operations during flush out?

Ruling

Several CIRs have addressed this issue, including CIR ruling 12/21/2004, "Note that LEED-NC prefers, but does not require, the flush to occur before furniture installation." The proposed furniture installation schedule, though not recommended, would still be acceptable under this credit. Applicable internationally.UPDATE 10/1/12: this LEED Interpretation is not applicable to LEED-CI. Furniture must be installed before the flush-out for LEED-CI projects.