Does a project have to purchase lamps during the performance period to earn the MRc4 Sustainable Purchasing - Reduced Mercury in Lamps?

Ruling

In a situation where no new lamps are needed, no, a project team does not need to purchase lamps solely to meet the requirements of the credit. The team must document that the purchasing policy is being followed by providing a letter signed by the responsible party confirming that no new lamps were purchased during the performance period. If new lamps were purchased, the project would follow the existing documentation requirements.