Inquiry

Is a campus-like approach for MRc2 acceptable for two LEED-NC v2009 registered projects each pursuing one-off certification? Space is limited on the urban site for recycling dumpsters, therefore the best approach for CWM may mean that waste and recycling for all LEED registered projects will need to be aggregated and tracked together. AGMBC Master Site / Campus is not utilized, yet we propose using the AGMBC precedent for MRc2 documentation. We propose to track together all demolition, construction waste/diverted, & land clearing material for the project and then apply a weighted average based on GSF to each LEED project.

Ruling

The applicant has requested to use a weighted average approach for Materials and Resources Credit 2 Construction Waste Management for several buildings that are pursuing one-off LEED Certification under LEED BD&C. Yes, the project may utilize a weighted approach based on gross floor area to determine the total construction waste for each building pursuing certification. For each LEED BD&C Building, the project team will be required to identify the materials that are diverted from disposal and provide calculations documenting the diversion rate. Each building must meet the required threshold for waste diversion in order to earn the credit. In addition, the Construction Waste Management (CWM) Plan must outline goals for diversion for each building, not just as an aggregate across all projects. Note that if the waste is comingled and sorted offsite, the project may follow the requirements outlined in LEED Interpretation 3000 for determining and documenting the diversion rate. This ruling addresses only projects pursing LEED Certification under the BD&C Rating Systems and does not set any precedent or guidelines for projects pursuing certification under different LEED Rating Systems. Applicable internationally.

Internationally Applicable
On
Campus Applicable
Off
Credits