FAQs about EAp2 :

The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

For a project outside the U.S., how do I determine the climate zone?

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

The Section 9 space-by-space method does not include residential space types. What should I use?

Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

Our project has a diesel backup generator. Should we include it in our energy model?

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

View answers »

Forum discussion

NC-2009 EAp2:Minimum Energy Performance

DES rates

Hi all,

We are working on a project that is being served by a district energy system both for heating and cooling.

The energy rates have been estimated according to the instructions provided within “Treatment of District or Campus Thermal Energy in LEED V2 and LEED 2009 - Design & Construction (DES v2), dated August 13, 2010”. Since a flat rate structure is being used for all energy sources (meaning the cost per unit energy is the same throughout the year, and there are no demand charges), then these flat rates simply become the virtual energy rates for the project. Hence, electricity rate is 0.18 $/kWh and natural gas rate is 0.07 $/kWh.

In terms of virtual DES rates, those have been calculated based on the equations found on page 14 of the same document:
District Chilled Water Rate:
• Units of $/ton-hour = Virtual Electric Rate (in $/kWh) x 0.85
District Hot Water Rate:
• Units of $/MBTU = Virtual Fuel Rate (in $/MBTU) x 1.59 + Virtual Electric Rate (in $/kWh) x 3

Given that 1 ton-hour equals 3.52 kWh and 1 MBTU equals 0.293 kWh we have concluded that:

District Chilled Water Rate should be set to 0.043 $/kWh and District Hot Water Rate to 1.95 $/kWh.

Are those calculations correct? If yes, this results in extremely high building energy costs which cannot be justified. Also, this would affect building's performance on the renewable energy credit (EAc5) as cost savings due to the PV system would be negligible compared to that huge total building energy cost.

Any ideas how to deal with this?

Thanks.

Kind regards,

Nikos

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Fri, 02/05/2021 - 18:01

Your district chilled water rate (0.043 $/kWh) is correct but your district hot water rate is incorrect and should be 0.113 $/kWh.  The natural gas rate of 0.07 $/kWh = 20.5 $/MBTU, so District hot water rate = (20.5 $/MBTU) x 1.59 + (0.18 $/kWh) x 3 = 33.135 $/MBTU which converts to 0.113 $/kWh.