Does the commitment letter be signed by the owner, which appears on the Project Details registered on LEEDOnline? We have a project which all the the decitions and policies are taken by a oganization manager which is signing the commitment letters applicable to WEp3, EAp3 and EQp2.
Is it ok if these commitment letters are signed by the organization manager or it has to be mandatory for registered owner to sign?
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5907 thumbs up
December 14, 2020 - 10:45 am
Ideally signed by the owner. If not I would assume that there should be some sort of letter designating the organization manager as the owner's representative inn these matters.
Sofia Barahona
B-green Chile8 thumbs up
December 14, 2020 - 12:52 pm
Thank you Marcus, everything clear, we will take in account having an additional designation letter by the owner.