Indoor Air Quality Assesment: Were are using path 2 During occupancy and we had 1 day were the outdoor humidity exceeded 60% RH. we continued to flush the building and added in addition hours of flushing with outdoor air below 60% RH and maintaining temperature between a low of 60 degrees and not above 80 degrees. Is this acceptable or do we need to restart the flush out after the one day spike in RH?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Rebecca Aarons-Sydnor
Project DirectorSustainable Design Consulting, LLC
LEEDuser Expert
32 thumbs up
August 19, 2021 - 9:46 am
You can stop and restart a flushout for things like commissioning tasks, so I'd assume you can also do this for other reasons, but you should include a narrative.