The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

For a project outside the U.S., how do I determine the climate zone?

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

The Section 9 space-by-space method does not include residential space types. What should I use?

Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

Our project has a diesel backup generator. Should we include it in our energy model?

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

View answers »

Forum discussion

NC-2009 EAp2:Minimum Energy Performance

DES allocation Calculator

Dear All,

 

I have a question regarding LEED V2009 BD+C New Construction and Major Renovation, EA P2 - Minimum Energy Performance.

 

We are working on a project pursuing LEED certification (NC v2009) using DES option 2 (aggregate building) and the monitoring method and we’re using the document “Treatment of District or Campus Thermal Energy in LEED V2 and LEED 2009 – Design & Construction”  as guide.

The building under certification is being built in a campus where a CCHP is already functioning and to which the Proposed Design will be connected. As such, we’ve developed a tool to try to allocate the fraction of hot water, chilled water and generated electricity to our building (and to associate the corresponding fuel cost), but since there isn’t an official template to do so, we’re not 100% sure.

However, we’ve noticed that there is an official USGBC tool used in O&M (“2009 and v4_DES Allocation Calculator”) for this allocation in existing buildings. Since O&M is intended for existing buildings, my suggestion is to use the energy simulation results as the “Building Metered Data” and check if the outputs match those from our tool and submit the calculator as evidence. Is this an acceptable approach?

 

Thanks for your attention.

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Thu, 09/12/2019 - 17:02

I'm not sure whether the O&M DES Allocation Calculator will produce the same results as the document “Treatment of District or Campus Thermal Energy in LEED V2 and LEED 2009 – Design & Construction”. I recommend checking the outputs as you mentioned to see if they match. If that is the case it should be acceptable.

Add new comment