NC-v4 WEp2:Indoor water use reduction

Cooling tower counted in WEp2?

Hi LEED experts, my factory has a cooling tower but it's for manufacture process, not for the HVAC system. Will this type of Cooling tower be taken into account for this Prerequisite? Thanks for your advice.

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 05/28/2019 - 20:48

if the cooling tower is within the project scope then yes, it would need to adhere to the prereq requirements regardless if it is a process cooling tower or HVAC cooling tower. 