The credit requires to submeter at least 2 of the following subsystems: irrigation, indoor plumbing fixtures and fittings, domestic hot water, boiler, reclaimed water, and other process water. An assessor has explicitly said that it has to be one of the subsystems mentioned, same as the credit language. However, if an office project only has indoor plumbing fixtures and fittings, and no irrigation (no landscape), no DHW, no boiler, no reclaimed water, and no process water. Can the project still vie for this point?

Furthermore, the next potential highest water consumption is the maintenance requirement used for building exterior, ACCUs, other equipment, etc. Would submetering this instead qualify to satisfy the credit requirement?