There's no such a building type as data centre in the base ratio table, I was wondering if it should be "data processing, telemarketing", or "general light industrial, industrial park, and manufacturing". Any idea?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Emily Purcell
Sustainable Design LeadCannonDesign
LEEDuser Expert
371 thumbs up
January 8, 2019 - 12:35 pm
I would use light industrial or maybe warehousing. Data processing is more of an office function and assumes densely occupied, the others are more accurate to data center by assuming low occupancy per square footage.
Ameet AA
41 thumbs up
January 8, 2019 - 8:10 pm
Thank you Emily. It makes sense to me.