Forum discussion

CI-v4 EQc6:Interior lighting

Option 1 requirements

I have a project that wants to get the score. Does the following strategy meet the needs?

1.Office has individual occupant spaces (workstations)
Install task lights which are dimmable or have at least three settings,But overhead light can't dimmable.
2.Data center
The overhead lighting is divided zones control,overhead light can't dimmable.

Thanks

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Add new comment

To post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.