FAQs about EAp2 :

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

The Section 9 space-by-space method does not include residential space types. What should I use?

Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

Our project has a diesel backup generator. Should we include it in our energy model?

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

Can I claim exterior lighting savings for canopy lighting even though a baseline model cannot include shading elements?

The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

View answers »

Forum discussion

NC-2009 EAp2:Minimum Energy Performance

Template v2009 EAp2 filling doubts

Hello, 

The HVAC system I'm modelling has two heat-pumps with a water side energy recovery device, so that it is possible to heat and cool (or dehumidify) the spaces simultaneously and recover energy from the condenser. However, I am unable to model this in the software, so I created a spreadsheet to estimate energy savings for space cooling and heating.

 

When filling out LEED v2009 template for EAp2 pre-requisit, should I fill Table EAp2-5 with wich values?

a) Should I enter values for space cooling and heating that appear in the simulation (without the effect of the energy recovery) and then I fill Table EAp2-10 under section 1.7 - Exceptional calculation measure summary with the energy savings?

b) Or should I enter in Table EAp2-5 directely the values that reflect energy consumption after the heat recovery and do nothing on Table EAp2-10?

 

Hope I made myself clear.

Thank you all in advance!

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 11/07/2017 - 15:33

This is an exceptional calculation. You should do a.

Wed, 08/29/2018 - 19:05

How do we show exceptional calculations when the new template no longer has a place to input them directly?

Fri, 09/07/2018 - 14:49

You enter the exceptional calculation values in the Performance Output tab of the Minimum Energy Performance Calculator.

Add new comment