Per the LEED certification Policy – we can submit construction review at Substantial Completion (defined as the date on which the building receives a Certificate of Occupancy or similar official indication that it is fit and ready for use.) Is a temporary certificate of occupancy (TCO) an acceptable milestone at which to submit for construction review?

2

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 12/06/2016 - 21:38

I spoke with a representative at USGBC and they confirmed that TCO is acceptable to submit for construction review.