We are working on a project in an undeveloped industrial area. It is a group of three very large logistic buildings, with warehouses and offices. There are currently no bus or rail stops within the LEED required distance, but talks are underway with the local authority to locate 2 bus stops near to the entrance of the site.
The LEED Reference Guide mentions planned rail or subway stops but doesn't mention planned bus stops. Are these valid to comply with the requirements of this credit?
Thank you!
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Marilyn Specht
Senior Principal | Director of Sustainability IntegrationSmithGroup
LEEDuser Expert
51 thumbs up
October 7, 2016 - 4:57 pm
Hi David, there was a post about this under the NC SSc4.1 discussion forum. Here's what was posted from a reviewer: "Note that bus routes that are not existing may not contribute to this credit. The allowance for lines that are planned and funded to be counted toward this credit applies only to rail lines."
David Lazaro
WSS REAL ESTATE6 thumbs up
October 10, 2016 - 5:15 am
Thank you very much Marilyn. We must have missed that post...thanks a lot for your help in recovering it