Dear all, I'm am modelling a project that is aiming to get EAp2 at design submittal with Tender Documentation LOD (Level of Detail), meaning there are lots of parameter only defined by technical specification. For example for glazing, 'U value should be below 1.8 W/m²K, and SHGC 0.25' or for Fan Coil Units, estimated pressure drop, maximum fan power, etc. Is it valid to do a submittal with this LOD on the ground that actual equipment/facade elements will perform as modelled or 'better', and therefore calculated saving are conservative? If so, would you submit an extra narrative describing in detail what was modelled (LOD) and why it is a conservative approach?