EBOMv2009 had a streamlined path option for projects that had previously achieved BD+Cv2009 Certification. Does that still exist for EBOMv4? And if so, what is available for projects that achieved v2009 certification but are seeking EBOMv4?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Trista Brown
Project DirectorWSP USA
456 thumbs up
January 17, 2017 - 4:01 pm
Great question! I asked GBCI about this last year and they responded that:
- An EBOM v4 project that achieved LEED BD+C v2009 certification can use the Streamlined Path for SSc4 Light Pollution Reduction ONLY. That's the only credit or prerequisite in the EBOM v4 Reference Guide with Streamlined Path language.
- An EBOM v4 project that achieved LEED BD+C v4 is also ONLY eligible to use the Streamlined Path for SSc4 Light Pollution Reduction, for the same reason.