Is the cutoff of "(2) years past substantial project completion" for construction review submittal strictly enforced? "Following completion of the Design Review phase and within 2 (two) years of substantial project completion, the Project Administrator shall submit, via LEED Online, a complete application for Construction Review "
It will be questioned and you will need to provide a narrative that explains the extenuating circumstances that kept the project team from submitting within the 2 years. Just getting around to submitting probably is not considered extenuating.