Our project was denied credit due to a failed pre-requisite during the final review. The client once us to file an appeal to address the pre-requisite. How long after the final review is submitted do you have to appeal and at what cost?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Charles Nepps
NH Green Consulting97 thumbs up
April 30, 2016 - 3:43 am
Normally you have 25 days to respond, but in my experience they are pretty flexible, so if you feel you need more time just contact them and let them know you're working on the appeal. The fee table shows appeals are $800 for complex credits, and $500 for all others...I would have to imagine a pre-requisite falls in the "all others" category.
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5909 thumbs up
May 1, 2016 - 6:06 pm
EAp2 and IEQp1 are the complex prerequisites.