Path 1 indicates flush-out needs to be accomplished with 14,000 cu ft. of OA per sq. ft. of floor area while maintaining an internal temperature of at least 60 deg F and no more than 60% RH. However, as I'm reading through Path 2, there is no mention of maintaining a certain internal temperature or relative humidity. When I go to submit the temperature and humidity readings using Path 2 along with all the supporting documentation, will I be denied credit for this point if I have any out of range temperature and/or humidity points even though Path 2 does not temperature and humidity limitations? Thanks!