We have a group CI project - 4 floors of one building and 1 smaller floor of a second building. A Central utility plan is being constructed for the tenants so we want to include it in our LEED scope of work. Question for this credit and others requiring that individual spaces within a group project must comply separately - how does the CUP play into this? Should it be included as a separate form, associated with one building, or both buildings?
I posted this yesterday but looks like it didn't go through - apologies if this is posted twice.
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5909 thumbs up
April 25, 2016 - 2:03 pm
I am not sure I understand your question. Not sure how you can pick and choose what is included in your scope of work. But that logic the whole building is being constructed for the tenants. Under CI you can only include what is within the scope of work of the CI project.
This particular forum is about lighting so perhaps you could post a more specific question in a more appropriate forum.