FAQs about EAp2 :

Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

Our project has a diesel backup generator. Should we include it in our energy model?

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

Can I claim exterior lighting savings for canopy lighting even though a baseline model cannot include shading elements?

The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

For a project outside the U.S., how do I determine the climate zone?

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

View answers »

Forum discussion

NC-2009 EAp2:Minimum Energy Performance

Elevation with more than 40% glazing

For a building with an elevation with 70% glazing and the others with less than 40%, how would the baseline elevations be modelled? Would the façade with 70% glazing be modelled with 40% glazing in the baseline and the other exactly as they are, or would all facades be modelled with proportionally reduced glazing so that in total (for all facades) glazing is 40% (although one facace may still exceed the 40% threshold)? In other words, would the façade with 70% glazing be modelled in the baseline with 70% as well, if the total percentage of glazing for all facades does not exceed 40% (in total)?

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 01/12/2016 - 22:00

See Table G3.1-5 Baseline (c). You distribute the 40% window area in the baseline model using the same proportions as the proposed design.

Wed, 01/13/2016 - 06:07

The way I like to think about it is surface for surface: - If a proposed case surface has glazing on it more than 40%, then reduce that glazing on that surface in the baseline to 40% - if a proposed case surface has glazing on it less than 40%, (this is true for both no glazing, i.e. zero or another percent like 38%), then the baseline is modeled EXACTLY the same In practice this means that the total is often a bit less than 40%.

Wed, 01/13/2016 - 08:12

Thanks. That said, in case the total glazing (all facades) is less than 40%, no reduction is required even if one single facade may exceed 40% glazing. On the other hand, in case the total glazing (all facades) exceeds 40%, the reduction will be proportional to all facades down to 40%, which means that even a single facade with less than 40% will be reduced by the same percentage as a facade exceeding 40%. Is that correct?

Wed, 01/13/2016 - 09:17

Looking in the Manual it says basically to reduce the m² for each and every window (above grade) by the same x% untill the total WWR of the (above grade) building is 40% or equal to the proposed case (as when the proposed case has less than 40%), whichever is smaller. 1. No baseline window may be larger than the proposed case window. It may be smaller.

Add new comment

To post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.