FAQs about EAp2 :

The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

For a project outside the U.S., how do I determine the climate zone?

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

The Section 9 space-by-space method does not include residential space types. What should I use?

Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

Our project has a diesel backup generator. Should we include it in our energy model?

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

View answers »

Forum discussion

NC-2009 EAp2:Minimum Energy Performance

Lighting Power Densities for an auditorium

Hi LEED experts! There is an auditorium in my project, also there will be a stage and a rehearsal. I have problems defining wich baseline ratio for ligthing according to table 9.6.1 Lighting Power Densities should i use. Should i use Audience/Seating Area or For Performing Arts Theater? both are great differents and i wonder how it show be selected or justified by the LEED reviewer? Besides, which option should i used for the lobby for that auditorium? Lobby or Lobby For Performing Arts Theater? Thanks you in advance! Dante Garcia LEED AP, BD+C

1

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Thu, 09/24/2015 - 17:02

A more thorough description of the project would be needed to provide an opinion. Is the primary function of the building a performing arts theater or is this an auditorium in another building type? For example a high school auditorium has a stage and rehearsal but it is not a performing art theater.

Thu, 09/24/2015 - 20:05

It is a goverment building for the peruvian council of science, technology and innovacion. Most spaces area offices. The auditorium is located inside of the building but has its own entrance door and HVAC systems. Thanks you Marcus! Dante

Thu, 09/24/2015 - 20:19

I think you have your answer. It is not a performing arts theater so you do not use those values.