NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy

Path2 - ventilation to begin 3 hours prior to occupancy

Our project is a resort with number of guest rooms, spas, restaurants , etc We are going with path 2 but there is a sentence under path 2 saying " During each day of the flush out period , ventilation must begin a minimum of 3 hours prior to occupancy and continue during occupancy" The question is when the guestroom is occupied 24/4 how can we start ventilation 3 hours prior to occupancy each day? Any clarification is greatly appreciated.

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Thu, 10/08/2015 - 20:36

If 24/7 just ventilate 24/7