Our project is a 30 year old building undergoing a Major Renovation and will be registered as LEED-NC v2009.
In calculating pre- and post-development runoff, do we consider the pre-development conditions of the site 30 years ago when the building was originally constructed (greenfield) or the site conditions before the renovation (existing building and grounds)?
Thank you.
Michael DeVuono
Regional Stormwater LeaderArcadis North America
LEEDuser Expert
187 thumbs up
July 2, 2015 - 6:43 pm
LEED does not establish criteria for determining pre-development runoff.
Calc the pre based on today's footprint, the post after development.
Leandro Silva
Novva Solutions17 thumbs up
July 3, 2015 - 2:26 pm
Thank you Michael.