FAQs about EAp2 :

The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

For a project outside the U.S., how do I determine the climate zone?

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

The Section 9 space-by-space method does not include residential space types. What should I use?

Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

Our project has a diesel backup generator. Should we include it in our energy model?

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

View answers »

Forum discussion

CS-2009 EAp2:Minimum Energy Performance

Lighting Energy Efficiency as a Lease requirement

We are compiling the LEED submission for an office tower that may have multiple tenants on each floor. Is it possible to claim tenant lighting energy efficiency savings through the inclusion of a lease requirement prior to any tenants actually being signed up? The credit asks for signed Lease agreements by both building owner and tenant which is of course not possible until tenants are actually signed up. Would it be acceptable to provide the following documentation as evidence instead: • Copy of generic Lease agreement that includes the above lighting efficiency requirement of tenants • Cover letter signed by PTPR clarifying that office tenants are let to be signed up but that their Lease agreements will include the above lighting energy efficiency requirements

2

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 04/14/2015 - 14:35

Yes you can provide a sample lease agreement along with a letter of commitment from the owner indicating that the sample will be used for all tenants.

Wed, 06/17/2015 - 15:18

Is there any official reference to this exception? Currently all forms with a provision to a lease agreement indicate that such an agreement has to be signed by both the developed and the tenant. That said would it be at the discretion of the reviewer to accept a sample of lease agreement along with a letter of commitment signed by the developer/owner only?

Wed, 06/17/2015 - 19:58

I am not sure if it is in writing anywhere. I can tell you that it is accepted by the reviewer in my experience. If not then every project would have to be fully leased before claiming any acceptable savings.

Wed, 06/17/2015 - 20:01

Thanks a lot Marcus!

Add new comment