FAQs about EAp2 :

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

Can I claim exterior lighting savings for canopy lighting even though a baseline model cannot include shading elements?

The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

For a project outside the U.S., how do I determine the climate zone?

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

The Section 9 space-by-space method does not include residential space types. What should I use?

Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

View answers »

Forum discussion

NC-2009 EAp2:Minimum Energy Performance

Baseline Return/Relief Fan Power

90.1 AppG G3.1.2.8 says the return/relief fan should be sized for max (SA-OA, 90%*SA) [cfm]. But in table 1.4. the allowable fan power is only based on the supply fan power. If I calculate the return/relief fan power based onG3.1.2.8, it will exceed the allowable fan power calculated by 1.4. So does anyone have a good approach how to deal with this?

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Mon, 02/23/2015 - 19:40

It sounds more complicated than it is. All it's really saying is that the baseline case needs to have the same fan configuration as the design and that the total fan power can't exceed the allowance. So if the design has supply, return and relief fans, then the baseline should also. The baseline power allowance should be allocated in the same proportion as it is in the design.

Mon, 02/23/2015 - 19:58

Thanks. That what I was hoping to do. But is there a rule of saying that I should use the same ratio as proposed or I can just arbitrarily set the supply and return/relief as long as the total is below the allowable fan power.

Tue, 02/24/2015 - 15:20

Making it proportional is a good practice. In the end it is not really required for LEED projects since it generally does not impact the baseline fan energy use.

Add new comment