Hello,
I am new to LEED and need some assistance before issuing for preliminary combined review. I have completed all the required project and pre-requisites forms. However to what extent do the other forms need to be completed to show that the minimum 40 points are being attempted? For example, I have completed EAc1.1 which gets 5 points+innovation point. However, in spite of the form being complete, the overall scorecard does not show that this credit has been attempted. Not sure how to change that. Any help will be greatly appreciated. Thank you
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Mike D
56 thumbs up
December 18, 2014 - 10:18 am
If the credit does not show on the scorecard, you can add the credit by clicking on Add/Remove credits below the scorecard tab
Aparna Maladkar
MissDecember 18, 2014 - 11:41 am
Thanks, it worked now!