We have a project- scope is 2 new buildings, no sitework/landscape. We accidentally registered it as one building, now the client does not want to pay/certify both buildings- just the main building. How do we delineate a LEED boundary for this? Can we draw the boundary directly around the one building we want to certify (which is our construction limit line for that individual building)? I'm not sure how we could include the existing site without including the second building or making it a campus, which we don't want to do.
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Kotaro,
can you tell me some more Information. Are the buildings directly attachet to each other ore stand alone buildings? It sounds like the second one. You can not certify 2 buildings under a single registration. You have to use the Multiple Buildings and On-Campus Building guideline.
They are standalone. We do not want to certify both buildings, just one of the two.
You should be able to define the limit of construction as the LEED boundary for that one project. All other data (SSp1, MRc2, MRc4, etc) should be limited to just that one project.
Add new comment
To post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.