I am working on a project where the LEED Boundary had already been set prior to my participation. The project is a Streetcar Vehicle maintenance facility owned on a City block owned by a City. The Masterplan of the the project indicates that a portion of the block could be developed by the city at a later date and leased to the managing company. The team set the LEED Boundary to exclude this entire half of the site because of the possibility of developing this future land.
I am not sure that we can exclude this part of the site from the LEED Boundary. The contractor is utilizing the entire site for construction/staging. They have also had to remove existing underground storage tanks from this area of the site for cleanup of the site.

Please let me know your thoughts. If you do believe that it would be acceptable, how would I document this. The Designer had assumed that we could use a campus or multiple buildings concept. But I believe that you have to document the multiple buildings on a master site to do this.