We are looking at an existing 300,000 s.f. hotel highrise in a downtown location that is currently on a citywide district steam utility. There are extensive interior architectural changes and a moderate amount of mechanical, so we are pursuing LEED NC. The thought is to install gas-fired boilers within the building, removing it from the (greatly inefficient) district system. Can this be modeled as an Option 1 DES in the baseline case, and an appropriate gas-fired boiler plant in the proposed? "Treatment of District or Campus Thermal Energy in LEED V2" does not seem to address this situation.