Hi. We are trying to assess the feasibility for LEED certification for a factory to be constructed on a developed footprint of 1.5 Acres on a site measuring 33 Acres. The site has been Master Planned to have more development of other factory units in future. How does one assess the Site credits for a project like this. Will the entire site be considered as part of the project compliance for LEED or just within the boundaries of the current project.
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Ellen Mitchell
331 thumbs up
February 17, 2014 - 12:53 pm
The form for SSc5.2 will ask you to confirm that all open space counted towards credit compliance be preserved for the life of the building. Because of this, I would suggest you draw your boundary to align with the current project only.