There are 50 units in a new rental apartment building for which the owner is seeking to achieve the credit for Enhanced Commissioning. Common areas do not pose a problem, but access to residential units might, especially 8-10 months after completion. Questions: 1. How many units should be subjected to commissioning tests, etc. 2. Should it be the exact same units that are tested just before the end of construction and post-construction? 3. May the units be occupied during the post-construction testing? 4. How many days are required to do post-construction testing in a unit?