Brown Field redevelopement

Hello, Due to budget issues, our client wants to decontaminate a portion of the site and not the entire site (only the areas were we are doing interventions). Would it be possible to achieve the credit only by remediateing to a portion of the site? Thank you

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Thu, 02/06/2014 - 04:41

Sahar, The only way I know where you can bypass remediating an entire project site would be to divide the site into two legal parcels, if possible. Then remediate the parcel where your project is located. The remaining parcel(s) would still be contaminated, but would not be included within the project boundary.

Thu, 02/06/2014 - 15:07

Thank you!