I would like to do the exam LEED AP and I have a very specific question :
FOR A PREVIOUSLY UNDEVELOPED SITE, WHAT WATER BODIES DO NOT HAVE TO MEET THE 50-FOOT SETBACK CRITERIA TO COMPLY SUSTAINABLE SITES CREDIT.CREDIT SITE SELECTION?.
Thank you
Forum discussion
I would like to do the exam LEED AP and I have a very specific question :
FOR A PREVIOUSLY UNDEVELOPED SITE, WHAT WATER BODIES DO NOT HAVE TO MEET THE 50-FOOT SETBACK CRITERIA TO COMPLY SUSTAINABLE SITES CREDIT.CREDIT SITE SELECTION?.
Thank you
LEEDuser is supported by our premium members, not by advertisers.
Go premium forTo post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.
April Brown
Sustainable Building ConsultantGreen Bridge Consulting
LEEDuser Expert
41 thumbs up
December 5, 2013 - 1:53 pm
Hi Elisa,
There is no qualification of the type of water body, the requirement is no development within 50 feet of any water body.
SSN Energy Model
Mechanical Engineer5 thumbs up
January 27, 2014 - 2:20 am
As defined in the Clean Water Act, small man – made water ponds such as those used in storm water retention, recreation & fire suppression are exempt from this requirement.