FAQs about EAp2 :

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

The Section 9 space-by-space method does not include residential space types. What should I use?

Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

Our project has a diesel backup generator. Should we include it in our energy model?

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

Can I claim exterior lighting savings for canopy lighting even though a baseline model cannot include shading elements?

The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

View answers »

Forum discussion

CS-2009 EAp2:Minimum Energy Performance

District Energy System with Thermal Energy Storage

I have a few questions regarding modeling of a LEED CS building using option #2 from the Treatment of District or Campus Thermal Energy in LEED guide. This is in regard to a DES that provides chilled water only. We have monitored the DES cooling plant for a complete year and have determined the average efficiency of the plant. A thermal energy storage tank is to be added to the cooling plant to shift the energy use to the off peak time period of the energy tariff. Under Option#2 of the LEED guide in section 2.4.2.2-4 would it be allowed to do the following: 1. Use the monitored averaged efficiency from the DES equipment in the proposed case energy model and 2. Model a thermal energy storage tank in the proposed case energy model sized to shift the cooling to the off peak time period and 3. Model the proposed case cooling equipment (chiller, pumps, cooling tower) as the same type as those in the DES with the chiller sized at 1.15 times the peak building load and 4. Separately meter the building and plant (in both proposed and baseline) with the associated building and DES energy tariffs (time of use based) tied to those meters?

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 09/17/2013 - 17:27

1-yes 2-yes 3-yes except you do not add the 15% oversizing. 4-I am not sure why you would need to create separate meters for the building and plant. The plant, including the thermal energy storage, is a virtual on-site plant under Option 2. Maybe I am not interpreting your last issue correctly.

Tue, 09/17/2013 - 18:46

Introduction of the separate meters allows the use of one utility tariff for the building and a separate tariff for the plant which is based on time of use. The plants utility tariff favors shifting of the energy used for cooling to the off peak demand window (which is what the TES is designed to do). This is an option under 2.4.2.2-(b). However the difference here is we don't have monitored average plant efficiencies for each utility time block for the plant with the TES because the TES is new to the existing plant. Therefore we propose to use the average plant efficiency (monitored from an entire year without TES) and add a virtual TES to the model because the simulation program is capable of modeling a TES.

Tue, 09/17/2013 - 19:24

Now it makes sense, thanks. If the tariffs are different then model it as close to the actual situation as possible. Make sure to use the identical rates in the baseline.

Add new comment