FAQs about EAp2 :

The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

For a project outside the U.S., how do I determine the climate zone?

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

The Section 9 space-by-space method does not include residential space types. What should I use?

Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

Our project has a diesel backup generator. Should we include it in our energy model?

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

View answers »

Forum discussion

NC-2009 EAp2:Minimum Energy Performance

Process Energy Savings, Alternative Compliance Path

Dear forum, We are working with an industrial plant that is seeking to obtain the LEED Certification. Since most of the energy consumption comes from process loads, we are using an Alternative Compliance Path to claim energy savings from the process equipment, comparing its performance with 4 similar industrial plants. Since the industrial plant produces beverages, the unit we are comparing is the energy consumption per liter of beverage produced (kWh/Liter). We believe this is a reasonable unit for comparing it to the other plants, since they all produce the same beverage. Do you think this approach will be accepted? Many thanks in advance.

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Mon, 09/02/2013 - 18:24

Maybe. It is a reasonable unit to compare plants but that does not make it reasonable for showing energy savings for a specific plant. In general the baseline for comparison when claiming process load savings should be "standard industry practice when building a new plant in your location". Comparing the process energy use to older plants may or may not be a valid comparison depending on the age and location of the existing plants.

Fri, 09/13/2013 - 16:16

Thanks for your comment Marcus, the other plants we are using for the comparison have changed their equipment in less than 5 years, so we think it will be valid. I do have another question, the energy consumption for process loads is approximately 95% of the total energy demand of the building, so, is it necessary to do the whole energy modeling process or just do the Exceptional Calculation Method?

Fri, 09/13/2013 - 16:24

You must model all of the energy use within and and associated with the project. So yes all of the process loads must be included. To claim any savings associated with the process you will need to follow the exceptional calculation method. Basically you will create a Proposed model which includes the process loads identical to the baseline process loads. You then do an exceptional calculation model which includes the items you are implementing to claim savings.

Add new comment