The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

For a project outside the U.S., how do I determine the climate zone?

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

The Section 9 space-by-space method does not include residential space types. What should I use?

Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

Our project has a diesel backup generator. Should we include it in our energy model?

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

View answers »

Forum discussion

NC-2009 EAp2:Minimum Energy Performance

Fan power BaseLine

Hello everybody, I´m simulating a LEED Project. When calculating the powers of the fans as G3.1.2.9, the result is adequate. Fans are constant flow, and the system is PSZ-HP (System 4). Analyzing the simulation results, the annual consumption of the fans are 30% of total consumption of base building, it really is a very high value if compared with the consumption of the proposed building fans. It is normal, these flows base building?

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 07/16/2013 - 14:32

That result is reasonable if the baseline are constant volume fans and the proposed are variable speed fans.

Tue, 07/16/2013 - 15:08

In this project, Proposed Building, fans are constant volumen too, but exist radiant floor anf fancoils. The total flow in baseline is 70 m3/s, and the total flow in proposed is 23 m3/s. The anual fan consumption in baseline is 500.000KWh The anual fan consumption in proposed is 30.000KWh Is it normal?? Thanks

Tue, 07/16/2013 - 15:34

A 94% reduction in fan energy use is not normal based on the information you provided. This level of claimed savings would be questioned in a LEED review. Make sure to double check the baseline fan power calculations.

Wed, 07/17/2013 - 07:18

To calculate fan power, the results of the G3.1.2.9 are total power (supply and exhaust) or I have to input these results to fan supply and fan exhaust independently ??? Thanks

Wed, 07/17/2013 - 12:55

The results are total fan power. You can check your results using the fan power calculator under the Documentation Toolkit in the header above.