The project would like to consider this credit. For that a PV system was previously installed and has been in operation within the performance period. The renewable energy system generates energy to help reduce the overall reliance on traditional energy. However, the total on-site renewable energy is only 2.3% of the total energy used. What should the project team do to obtain this credit and still make use of the benefits of the PV system even if the production is less than the 3% required to obtain 1 point? thanks