FAQs about EAp2 :

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

The Section 9 space-by-space method does not include residential space types. What should I use?

Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

Our project has a diesel backup generator. Should we include it in our energy model?

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

Can I claim exterior lighting savings for canopy lighting even though a baseline model cannot include shading elements?

The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

View answers »

Forum discussion

CS-2009 EAp2:Minimum Energy Performance

Table 1.4

Hi Eveybody, I have sent my first energy modeling, and a few commens came back, One of them referred to VAV fan powered terminals, and I copy textually the comment: "Insufficient informatin is provided in Supplemental Table 1.4 regarding VAV fan powered terminals. For both the Baseline and the Proposed Case, indicate in Table 1.4 the fan power per cfm for the parallel fan-powered boxes, the peak air flow as a percentaje o design flow, and the minimum volume setpoints as a percentaje of peak design flow, and verify ... ", The question is, were in Table 1.4 this data is asked for???, I have inserted the corresponding System 8 in the Baseline equipment cell, but no data for corresponding VAV boxes is asked for anyware I can see, Thank you, Paula

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Fri, 06/07/2013 - 16:23

Table 1.4 (the older one, not the new one) was never intended to "request" all of the summary information needed for a model in all cases. It should be modified to reflect the major modeling inputs for your specific project. Its purpose is to provide a summary of those major modeling inputs. In this specific case Table 1.4.2 does have a line for Zone Terminal Boxes Fan Power. This is where the requested information should be entered.

Fri, 06/07/2013 - 16:40

Thank you Marcus!!